Internet and Intranet services
The primary objectives of this subprogramme is to increase the interest and access by governments, the UN system, and the public-at-large to UN materials and information, as well, as preservation of the Organization’s intellectual property rights.
The expected accomplishments by the end of the plan period would include an increase in coverage of the Organization activities and public awareness about the UN issues.
Indicators of achievement would include number of access to the UN Intranet and Internet sites; an increase in number of inquires and request for UN materials and information; as well, as positive feedback from the users.
Internet
The primary objectives of the UN web site operation and development are: global and easy access by governments, the UN system, and the public-at-large to UN materials and information, as well, as preservation of the Organization’s intellectual property rights.
To ensure successful development of the UN web site the following activities are envisioned:
Research and introduction of new technologies to
enable
implementation of dynamic UN web site with personalized,
up-to-the-minute interactive web pages, which have fresh information from the
Headquarters and offices in Geneva, Vienna and other locations;
Research and introduction of a new multimedia technology on the UN web site, that will allow the direct delivery worldwide of breaking news and media products, including live transmissions and complete multimedia coverage of United Nations activities;
Introduction of Wireless Application Protocol (WAP)
and other protocols to enable access of the hand-held mobile devices anywhere
in the world to the latest information on United Nations;
In-house development of Ad-hoc Internet applications in order to improve functionality of the UN web site.
1.
Research and introduction of new
technologies to enable
implementation of dynamic UN web site with personalized,
up-to-the-minute interactive web pages. Total $367,000; C-8; P-6; G-6
Activities:
1.A Business analysis
Tasks:
1.A.1 Define user requirements and conduct feasibility study C-1.5
Consultant $45,000
1.A.2 Research and evaluation of new technologies P-0.25
Knowledge acquisition $7,000
1.A.3 Analysis of the hardware and software requirements P-0.25 G-1
1.A.4 Evaluation of the infrastructure and technical support requirements P-0.25
1.A.5 Evaluation and analysis of recommendations P-0.25
1.B Design new system
Tasks:
1.B.1
Design necessary applications for UN web site, C-1.5 P-0.25
based on recommendations and in-house analysis
Contractor $45,000
1.B.2 Design review with users and management P-0.25 G-0.5
1.C Development
1.C.1
Creation of development environment needed for testing
new web technologies and applications P-0.75 G-1.5
Hardware and software $70,000
1.C.2
Development of the applications and its testing on the
UN development web site. C-5 P-0.25 G-0.5
Contractor $150,000
1.D Deployment
1.D.1 Prepare documentation for operation and users training P-0.5 G-0.5
1.D.2 Deployment of the applications in the operation environment P-0.25 G-0.5
1.E Project management
1.E.1 Prepare RFP P-0.25
1.E.2 Manage the project P-1.5
1.F Maintenance of new applications
1.F.1 Preparation of documentation for authoring departments. P-0.5 G-0.5
1.F.2 Training of staff involved in maintenance of new applications P-0.25 G-0.5
1.F.3 Second level of operational support to application P-0.25 G-0.5
2.
Research and
introduction of new technologies for direct
multimedia coverage of United Nations activities. Total $227,000;
C-6; P-6; G-6
Activities:
2.A Business analysis
Tasks:
2.A.1 Define user requirements and conduct feasibility study C-1
Consultant $30,000
2.A.2 Research and evaluation of multimedia technologies P-0.25
Knowledge acquisition $7,000
2.A.3 Analysis of the hardware and software requirements P-0.25 G-1
2.A.4 Evaluation of the infrastructure and technical support requirements P-0.25
2.A.5 Evaluation and analysis of recommendations P-0.25
2.B Design new system
Tasks:
2.B.1
Design a multimedia application for UN web site,
based on recommendations and in-house analysis C-1 P-0.25
Contractor $30,000
2.B.2 Design review with users and management P-0.25 G-0.5
2.C Development
2.C.1
Creation of development environment needed for testing
multimedia technologies and application P-0.75 G-1.5
Hardware and software $40,000
2.C.2
Development of a multimedia application and its testing on the
UN development web site. C-5 P-0.25 G-0.5
Contractor $150,000
2.D Deployment
2.D.1 Prepare documentation for operation and users training P-0.5 G-0.5
2.D.2 Deployment of the applications in the operation environment P-0.25 G-0.5
2.E Project management
2.E.1 Prepare RFP P-0.25
2.E.2 Manage the project P-1.5
2.F Maintenance of multimedia applications
2.F.1 Preparation of documentation for authoring departments. P-0.5 G-0.5
2.F.2 Training of staff involved in maintenance of new applications P-0.25 G-0.5
2.F.3 Second level of operational support to application P-0.25 G-0.5
3. Research
and introduction of Wireless Application Protocol (WAP)
in order to enable access of the hand-held mobile devices anywhere
in the world to the latest information on United Nations activities.
Total $247,000; C-7; P-6; G-6
Activities:
3.A Business analysis
Tasks:
3.A.1 Define user requirements and conduct feasibility study C-1
Consultant $30,000
3.A.2 Research and evaluation of new technologies P-0.25
Knowledge acquisition $7,000
3.A.3 Analysis of the hardware and software requirements P-0.25 G-1
3.A.4 Evaluation of the infrastructure and technical support requirements P-0.25
3.A.5 Evaluation and analysis of recommendations P-0.25
3.B Design new system
Tasks:
3.B.1
Design WAP-enabled applications for UN web site,
based on recommendations and in-house analysis C-1 P-0.25
Contractor $30,000
3.B.2 Design review with users and management P-0.25 G-0.5
3.C Development
3.C.1
Creation of development environment needed for testing
new web technologies and applications P-0.75 G-1.75
Hardware and software $30,000
3.C.2
Development of WAP-enabled applications and their testing
on the UN development web site. C-5 P-0.25 G-0.5
Contractor $150,000
3.D Deployment
3.D.1 Prepare documentation for operation and users training P-0.5 G-0.5
3.D.2 Deployment of the applications in the operation environment P-0.25 G-0.5
3.E Project management
3.E.1 Prepare RFP P-0.25
3.E.2 Manage the project P-1.5
3.F Maintenance of WAO-enabled applications
3.F.1 Preparation of documentation for authoring departments. P-0.5 G-0.5
3.F.2 Training of staff involved in maintenance of new applications P-0.25 G-0.5
3.F.3 Second level of operational support to application P-0.25 G-0.5
- Development of
ad-hoc applications based on the users’ demand
and maintenance of existing applications P-6; G-6
Activities:
4.A Business analysis
Tasks:
4.A.1 Analysis of user requirements conduct feasibility study P-0.25
4.A.2 Research and evaluation of existing technologies P-0.15
4.A.3 Analysis of the hardware and software requirements P-0.1 G-0.5
4.A.4 Evaluation of the infrastructure and technical support requirements P-0.15 G-0.5
4.A.5 Recommendations on applications development P-0.1
4.B Design new applications
Tasks:
4.B.1 Design applications for UN web site, based on in-house analysis P-0.5
4.B.2 Design review with users and management P-0.25
4.C Development
4.C.1
Creation of development environment needed for testing
new web technologies and applications P-0.25
4.C.2
Development of the applications and its testing on the P-3.25 G-3
UN development web site.
4.D Deployment
4.D.1 Prepare documentation for operation and users training P-0.25 G-0.5
4.D.2 Deployment of the applications in the operation environment P-0.25 G-0.5
4.E Maintenance of existing applications
4.E.1 Troubleshooting and support of developed applications G-1
4.E.2 Consultations and assistance to authoring departments P-0.25
4.E.3 Enhancement of the applications P-0.25